To enforce and run the production line of Abadeh’s certain types of industrial ceramics in phase 1 and 2:
 
Project Specifications (Phase 1):
Production capacity 1000 tons
Location Abadeh
Main product Packing, ceramic ball, and some related parts
Contract year 2006
Estimated investment 10 Billion Rials
Production time 2009
 
Project Specifications (Phase 2):
Production capacity 1500 tons
Location Abadeh
Main product Packing, ceramic ball, and some related parts
Contract year 2006
Estimated investment 20 Billion Rials
   
Other Projects
To develop technical and economical justifications for producing ceramic insulators utilized in power industry

To develop technical and economical justifications for producing Sadafe Abadeh’s Sanitary ware

To develop technical and economical justifications for producing Sadafe Abadeh’s Sanitary ware

To enforce and run the production line of Abadeh’s certain types of industrial ceramics in phase 1 and 2

To develop technical and economical justifications for producing some types of corrosion-resistant ceramics (anti-acid)

To develop technical and economical justifications for producing certain types of ceramics utilized in construction industry

To develop technical and economical justifications for producing ceramic rollers and some wares utilized for furnishing ceramic kilns

To develop technical and economical justifications for producing industrial ceramics for Raahbaran Novin Mehr Company

  Projects’ Progress Chart